Boggy Point Boat Launch Pilings
By Alabama Marine Resources
 
February 28, 2019 - Orange Beach, AL - (OBA®) - The Marine Resources Division (MRD) maintains a number of public boat ramps in coastal Alabama including the Boggy Point Boat Ramp.
 
In May 2018, MRD staff inspected the piers at the Boggy Point Boat Ramp which were installed in 2006 and discovered that the pilings and the support bracing for the decking were nearing the end of their usable life.
 
The decision to replace all finger pier structures was made at that time and federal funding from the Fish and Wildlife Service’s Sport Fish Restoration Program was identified for grant request submission. The funds; however, for this project were not available until January 1, 2019.
 
During development of the federal grant application and the grant approval process, MRD staff coordinated with US Army Corps of Engineers staff for permit requirements and Department of Conservation and Natural Resources (DCNR) Engineering Section staff to redesign the pier to increase the new piers’ longevity and minimize maintenance costs.
 
The grant award received final approval and became effective for use beginning January 1, 2019. A pre-bid meeting was held with interested contractors January 3, 2019. The final bid approval was received by MRD on February 25th. The total cost for the current repairs (including repairs to the parking lot) is $175,795 of which the Marine Resources Division is responsible for 25%.
 
“There is never a good time to close a boat ramp in coastal Alabama,” said MRD Director Scott Bannon. Director Bannon added “We did everything we could do prior to the funds being approved to ensure we could begin the repairs as soon as funding was secured.
 
Our assessment of the pier’s condition was that it was not in the best interest of public safety to delay the repairs until after the summer.” “We will work with the contractor to expedite the repairs to minimize impacts to those who utilize the ramp.”