Reroute of Canal Road around Gulf Shores neighborhood in limbo

John Mullen • April 29, 2022

Plans are in place for a temporary reroute

Reroute of Canal Road around Gulf Pines neighborhood in Gulf Shores, Alabama, is in limbo.

Gulf Shores, Ala. – (OBA) – Frustration with the Alabama Department of Transportation was a common theme when Gulf Shores conducted a town hall meeting to inform residents of upcoming road and infrastructure projects.


Besides the canceling of the third bridge project, ALDOT also backed off on funding support for a vital cog in three interconnected projects the city is looking to build by 2024.


RELATED STORY: ALDOT's $20 million bluff killed second Gulf Shores bridge


“I don’t want you to get too frustrated,” Mayor Robert Craft told the crowd at the April 19 town hall “but join me in a little frustration.”


If the city wants to add a third lane to southbound State Route 59, it will have to provide another safe pedestrian and bicycle access over the Intracoastal Waterway. A plan is in place to build that access as a freestanding bridge over the waterway near Tacky Jacks and Big Beach Brewing on the south and LuLu’s on the north.


But the big plaza and ADA friendly ramps will take up the vital 90-degree turn at Canal Road and East Second Street virtually cutting off one of two east-west connections between Gulf Shores and Orange Beach.


The solution to that problem is a bypass around the Gulf Pines or Meyer Park neighborhood one ALDOT, Craft said, agreed to help fund.


“We have joint partnerships with ALDOT to build that road, Canal Road reroute, Craft said. “We had this road planned and it was going to be jointly funded by a RESTORE grant that the city got as well as with ALDOT’s participation. It was designed to go from Fort Morgan Road all the way back up to the new bridge or to the toll bridge if the new bridge wasn’t built. That’s come apart because ALDOT is not willing to now fund that road or help fund that road.”


The third southbound is going out to bid soon and the pedestrian bridge is in the design stage and awaiting word on permit applications from Army Corps of Engineers and the Coast Guard.


But the road that will skirt Gulf Pines to the south?


“It’s mandatory that we reroute this road because when we build (the pedestrian bridge) you can’t get around that corner anymore,” Craft said.


But there is no schedule on the design, bidding and construction of this final cog of these three vital projects.


“To be determined on where we are on that,” Craft said. “We have no timeframe to be able to talk about that because we just don’t know. We spent a lot of time with this neighborhood trying to let the neighborhood to give us input on where this road needs to go. We worked great with the state park to endorse allowing us to go through there.”


But no solid plan to execute this new bypass is in place. When construction begins on the pedestrian bridge a temporary bypass will be in place, Craft said.


THIRD SOUTHBOUND LANE


Craft said this new lane will be built in two phases with the first phase going out for bid this summer with the first phase going from Cypress Bend Drive or the Target entrance to Fort Morgan Road.


‘It will help us getting over that bridge back and forth by adding a third lane,” Craft said. “The schedule on that is we will actually open our bids April 26 for phase one of this project. The design is complete, we’ll start construction in June of this year and end construction in August of 2024. The construction sequencing will begin with the utility work that will be in the right of ways and the utility work and that will take approximately six months and then we’ll have to phase over to start working on the roadway.”


Craft said work on moving utilities will be done in the day time but the actually road work will be done overnight when traffic is not as heavy.


“We’re only be working these crews at night,” Craft said “We won’t be working during the day but there will still be challenges in getting around.”


The second phase of the work from Target north to Coastal Gateway Boulevard will be managed by ALDOT, Craft said.


PEDESTRIAN BRIDGE


“Obviously, we can’t connect over the bridge until we finish our pedestrian bridge so we can relocate bicycles and pedestrians safely to another way to get across,” Craft said. “So, the next thing on the schedule for us to build is the pedestrian bridge at Waterway Village. It spans the Intracoastal in the location of the old drawbridge.”


The design for the span is expected to be finished this summer with hopes of starting construction this winter and completion by the winter of 2024. All of the plans are at the mercy of permits from the Army Corps of Engineers and the Coast Guard which are notoriously slow in coming.

Share this article w/ Friends...

By R. Ken Cooper May 20, 2026
Alabama voters have decided major state races, but will head back to the polls for several runoffs.
Chef Robbie Nicolaisen and sous chef Gabe Atkinson accept the award
By OBA Staff May 20, 2026
Orange Beach, Ala. — (OBA) — The Sweet Grown Alabama Seafood Cook-Off drew a large crowd to The Wharf for a night celebrating Alabama seafood and the people who help produce it. The event honored chefs, fishermen, farmers, and other producers from across the state.
Orange Beach Police Cruiser
By R. Ken Cooper May 20, 2026
Orange Beach, Ala. — (OBA) — The Orange Beach Police Department (OBPD) has launched a new recruitment campaign seeking police officers to join its force in one of Alabama's most popular coastal cities. Department officials are looking for candidates dedicated to public service and committed to fostering strong communi
Foley is preparing to build sidewalks linking the Mills Community with other areas of
the city.
By Guy Busby May 20, 2026
Foley, Ala. — (OBA) — Foley is moving ahead with a sidewalk project. The work focuses on the Mills Community in west Foley. City officials said the route will connect to other walkways and lead to a planned community park. Mills residents voted in 2023 to annex their community into Foley. Mayor Ralph Hellmich said cit
Orange Beach Lady Makos Softball Team is a 6-Time State Champs
By John Mullen May 19, 2026
Oxford, Ala. – (OBA) – Among Alabama softball teams and consecutive state titles, the Orange Beach Lady Makos stand taller than any program. Orange Beach completed its sixth straight tournament by going undefeated at the state tournament site here on May 18-19.
CoastAL Restaurant Orange Beach
By R. Ken Cooper May 19, 2026
Orange Beach, Ala. — (OBA) — A restaurant sitting right on the Gulf in Orange Beach, Alabama, has earned a spot on a national list of the best waterfront restaurants in the United States. CoastAL Restaurant in Orange Beach is located on the beautiful Gulf. It sits directly on the beach, where guests can walk straight
Canall Road Cutoff - Stock Image
By John Mullen May 19, 2026
One of several topics covered by Kennon at the city’s May 6 town hall included a spur of a road to take two lanes south from Canal Road near Big Mike’s Steakhouse to a meeting with State Route 161. From there, the stream of traffic will continue to flow with two lanes of traffic heading south to the State Route 182 or
Orange Beach City Hall
By John Mullen May 19, 2026
Orange Beach, Ala. – (OBA) – Orange Beach will utilize a grant from the U.S. Department of Transportation to help develop a safety action plan in the city. The funds will come from the department’s Safe Streets and Roads for All grant program and will require a city match.
2026 Orange Beach Lady Makos Softball Team
By John Mullen May 19, 2026
Oxford, Ala. – (OBA) – Orange Beach is poised to make history with a chance to claim a sixth straight Alabama softball state championship. The Lady Makos struggled at times at the plate, got stellar pitching from MK McMullan, and pounded out timely hits in two big innings to go 3-0 on the day and a date in the champion
Red Clay Strays
By R. Ken Cooper May 18, 2026
Orange Beach, Ala. — (OBA) — Three acts from Alabama walked away as big winners at the 61st Academy of Country Music Awards. The show took place this past weekend at the MGM Grand Garden Arena in Las Vegas. Shania Twain hosted the ceremony, which streamed live on Prime Video. It was a strong night for the state, with
Show More