Reroute of Canal Road around Gulf Shores neighborhood in limbo

John Mullen • April 29, 2022

Plans are in place for a temporary reroute

Reroute of Canal Road around Gulf Pines neighborhood in Gulf Shores, Alabama, is in limbo.

Gulf Shores, Ala. – (OBA) – Frustration with the Alabama Department of Transportation was a common theme when Gulf Shores conducted a town hall meeting to inform residents of upcoming road and infrastructure projects.


Besides the canceling of the third bridge project, ALDOT also backed off on funding support for a vital cog in three interconnected projects the city is looking to build by 2024.


RELATED STORY: ALDOT's $20 million bluff killed second Gulf Shores bridge


“I don’t want you to get too frustrated,” Mayor Robert Craft told the crowd at the April 19 town hall “but join me in a little frustration.”


If the city wants to add a third lane to southbound State Route 59, it will have to provide another safe pedestrian and bicycle access over the Intracoastal Waterway. A plan is in place to build that access as a freestanding bridge over the waterway near Tacky Jacks and Big Beach Brewing on the south and LuLu’s on the north.


But the big plaza and ADA friendly ramps will take up the vital 90-degree turn at Canal Road and East Second Street virtually cutting off one of two east-west connections between Gulf Shores and Orange Beach.


The solution to that problem is a bypass around the Gulf Pines or Meyer Park neighborhood one ALDOT, Craft said, agreed to help fund.


“We have joint partnerships with ALDOT to build that road, Canal Road reroute, Craft said. “We had this road planned and it was going to be jointly funded by a RESTORE grant that the city got as well as with ALDOT’s participation. It was designed to go from Fort Morgan Road all the way back up to the new bridge or to the toll bridge if the new bridge wasn’t built. That’s come apart because ALDOT is not willing to now fund that road or help fund that road.”


The third southbound is going out to bid soon and the pedestrian bridge is in the design stage and awaiting word on permit applications from Army Corps of Engineers and the Coast Guard.


But the road that will skirt Gulf Pines to the south?


“It’s mandatory that we reroute this road because when we build (the pedestrian bridge) you can’t get around that corner anymore,” Craft said.


But there is no schedule on the design, bidding and construction of this final cog of these three vital projects.


“To be determined on where we are on that,” Craft said. “We have no timeframe to be able to talk about that because we just don’t know. We spent a lot of time with this neighborhood trying to let the neighborhood to give us input on where this road needs to go. We worked great with the state park to endorse allowing us to go through there.”


But no solid plan to execute this new bypass is in place. When construction begins on the pedestrian bridge a temporary bypass will be in place, Craft said.


THIRD SOUTHBOUND LANE


Craft said this new lane will be built in two phases with the first phase going out for bid this summer with the first phase going from Cypress Bend Drive or the Target entrance to Fort Morgan Road.


‘It will help us getting over that bridge back and forth by adding a third lane,” Craft said. “The schedule on that is we will actually open our bids April 26 for phase one of this project. The design is complete, we’ll start construction in June of this year and end construction in August of 2024. The construction sequencing will begin with the utility work that will be in the right of ways and the utility work and that will take approximately six months and then we’ll have to phase over to start working on the roadway.”


Craft said work on moving utilities will be done in the day time but the actually road work will be done overnight when traffic is not as heavy.


“We’re only be working these crews at night,” Craft said “We won’t be working during the day but there will still be challenges in getting around.”


The second phase of the work from Target north to Coastal Gateway Boulevard will be managed by ALDOT, Craft said.


PEDESTRIAN BRIDGE


“Obviously, we can’t connect over the bridge until we finish our pedestrian bridge so we can relocate bicycles and pedestrians safely to another way to get across,” Craft said. “So, the next thing on the schedule for us to build is the pedestrian bridge at Waterway Village. It spans the Intracoastal in the location of the old drawbridge.”


The design for the span is expected to be finished this summer with hopes of starting construction this winter and completion by the winter of 2024. All of the plans are at the mercy of permits from the Army Corps of Engineers and the Coast Guard which are notoriously slow in coming.

Share this article w/ Friends...

Makos on Main
By K. Cooper July 23, 2026
Orange Beach, Ala. — (OBA) — Orange Beach City Schools invites students, staff, and the community to celebrate the start of the school year at the annual Makos on Main Parade. The event will be held at The Wharf in Orange Beach and is free and open to the public. Students from Pre-K through 12th grade will march toget
Orange Beach Officers secure a boat that got loose during T.S. Bertha
By K. Cooper July 23, 2026
Orange Beach, Ala. — (OBA) — An Orange Beach resident, Maria Hawkins, found more than she expected while checking their property Wednesday morning after Tropical Storm Bertha. A boat had washed up near their dock overnight. Hawkins spotted it after waking up and stepping outside to survey the damage. What followed was
Gulf Spanish Mackerel - Photo by Shutterstock
By K. Cooper July 23, 2026
Orange Beach, Ala. — (OBA) — NOAA Fisheries is inviting the public to weigh in on a proposed rule that would reduce the annual catch limit for Gulf Spanish mackerel. The proposed change is part of Framework Amendment 14 to the Fishery Management Plan for Coastal Migratory Pelagic Resources of the Gulf and Atlantic Reg
Tropical Storm Birtha's Current Position
By K. Cooper July 22, 2026
Orange Beach, Ala. — (OBA) — Tropical Storm Bertha, the second named storm of the 2026 Atlantic hurricane season, was located due south of Dauphin Island and just southwest of Orange Beach as of 4 a.m. CDT this morning. The NWS National Hurricane Center in Miami issued Advisory 12, placing the storm's center near lati
Gulf Shores International Airport
By Erica Thomas July 22, 2026
Gulf Shores, Ala. — (OBA) — Officials with the Gulf Shores International Airport (GUF/JKA) broke ground on a $15 million terminal expansion in response to “extraordinary” passenger growth.
Extension - Alabama A&M and Auburn Universities
By K. Cooper July 22, 2026
Orange Beach, Ala. — (OBA) — Watching a cluster of balloons drift over the Gulf may feel like a fitting tribute or a joyful celebration, but researchers say the practice causes lasting harm to wildlife and the environment. The Alabama Cooperative Extension System published a report, warning that every balloon released
Bertha is the second named storm of the 2026 Atlantic hurricane season
By K. Cooper July 21, 2026
Orange Beach, Ala. — (OBA) — Tropical Storm Bertha was about 175 miles southeast of Mobile, Alabama, as of 7 a.m. CDT on Tuesday, July 21, 2026. The National Hurricane Center in Miami issued Intermediate Advisory 8A at that time, placing the storm's center near latitude 28.8 North, longitude 86.2 West. Maximum sustain
Judi Bolton Wheat Honored at American Legion Post in Foley
By K. Cooper July 21, 2026
Foley, Ala. — (OBA) — An Elberta woman has been named the American Legion Auxiliary Volunteer of the Year for the State of Alabama. Judi Wheat received the honor at a recent district meeting at American Legion Post 99 in Foley. Alabama State American Legion Auxiliary President Carla Biniecki presented the award. Famil
Irwin Street Speed Limit Reduced
By Guy Busby July 21, 2026
Foley, Ala. — (OBA) — The City of Foley has lowered the speed limit on Irwin Street to improve access for low-speed vehicles. The Foley City Council gave final approval to an ordinance implementing the change. The new limit is 35 miles per hour, down from 40 miles per hour. Mayor Ralph Hellmich said the lower limit wi
Orange Beach City Hall
By K. Cooper July 21, 2026
Orange Beach, Ala. — (OBA) — Orange Beach is taking its next step toward environmental preservation. The City Council will vote on a resolution awarding an $84,297.04 bid to Integrated Aqua Systems, Inc., for life-support equipment at the Coastal Alabama Sea Turtle Facility. This project underscores the city's commitm
Show More