Reroute of Canal Road around Gulf Shores neighborhood in limbo

John Mullen • April 29, 2022

Plans are in place for a temporary reroute

Reroute of Canal Road around Gulf Pines neighborhood in Gulf Shores, Alabama, is in limbo.

Gulf Shores, Ala. – (OBA) – Frustration with the Alabama Department of Transportation was a common theme when Gulf Shores conducted a town hall meeting to inform residents of upcoming road and infrastructure projects.


Besides the canceling of the third bridge project, ALDOT also backed off on funding support for a vital cog in three interconnected projects the city is looking to build by 2024.


RELATED STORY: ALDOT's $20 million bluff killed second Gulf Shores bridge


“I don’t want you to get too frustrated,” Mayor Robert Craft told the crowd at the April 19 town hall “but join me in a little frustration.”


If the city wants to add a third lane to southbound State Route 59, it will have to provide another safe pedestrian and bicycle access over the Intracoastal Waterway. A plan is in place to build that access as a freestanding bridge over the waterway near Tacky Jacks and Big Beach Brewing on the south and LuLu’s on the north.


But the big plaza and ADA friendly ramps will take up the vital 90-degree turn at Canal Road and East Second Street virtually cutting off one of two east-west connections between Gulf Shores and Orange Beach.


The solution to that problem is a bypass around the Gulf Pines or Meyer Park neighborhood one ALDOT, Craft said, agreed to help fund.


“We have joint partnerships with ALDOT to build that road, Canal Road reroute, Craft said. “We had this road planned and it was going to be jointly funded by a RESTORE grant that the city got as well as with ALDOT’s participation. It was designed to go from Fort Morgan Road all the way back up to the new bridge or to the toll bridge if the new bridge wasn’t built. That’s come apart because ALDOT is not willing to now fund that road or help fund that road.”


The third southbound is going out to bid soon and the pedestrian bridge is in the design stage and awaiting word on permit applications from Army Corps of Engineers and the Coast Guard.


But the road that will skirt Gulf Pines to the south?


“It’s mandatory that we reroute this road because when we build (the pedestrian bridge) you can’t get around that corner anymore,” Craft said.


But there is no schedule on the design, bidding and construction of this final cog of these three vital projects.


“To be determined on where we are on that,” Craft said. “We have no timeframe to be able to talk about that because we just don’t know. We spent a lot of time with this neighborhood trying to let the neighborhood to give us input on where this road needs to go. We worked great with the state park to endorse allowing us to go through there.”


But no solid plan to execute this new bypass is in place. When construction begins on the pedestrian bridge a temporary bypass will be in place, Craft said.


THIRD SOUTHBOUND LANE


Craft said this new lane will be built in two phases with the first phase going out for bid this summer with the first phase going from Cypress Bend Drive or the Target entrance to Fort Morgan Road.


‘It will help us getting over that bridge back and forth by adding a third lane,” Craft said. “The schedule on that is we will actually open our bids April 26 for phase one of this project. The design is complete, we’ll start construction in June of this year and end construction in August of 2024. The construction sequencing will begin with the utility work that will be in the right of ways and the utility work and that will take approximately six months and then we’ll have to phase over to start working on the roadway.”


Craft said work on moving utilities will be done in the day time but the actually road work will be done overnight when traffic is not as heavy.


“We’re only be working these crews at night,” Craft said “We won’t be working during the day but there will still be challenges in getting around.”


The second phase of the work from Target north to Coastal Gateway Boulevard will be managed by ALDOT, Craft said.


PEDESTRIAN BRIDGE


“Obviously, we can’t connect over the bridge until we finish our pedestrian bridge so we can relocate bicycles and pedestrians safely to another way to get across,” Craft said. “So, the next thing on the schedule for us to build is the pedestrian bridge at Waterway Village. It spans the Intracoastal in the location of the old drawbridge.”


The design for the span is expected to be finished this summer with hopes of starting construction this winter and completion by the winter of 2024. All of the plans are at the mercy of permits from the Army Corps of Engineers and the Coast Guard which are notoriously slow in coming.

Share this article w/ Friends...

Canal Road To Temporarily Close For Bridge Work
By OBA Staff February 19, 2026
Orange Beach, Ala. — (OBA) — Canal Road between Gulf Shores and Orange Beach will close temporarily so crews can safely continue work on the new Intracoastal Waterway Bridge. The Alabama Department of Transportation says the short-term shutdown is needed to allow contractors to work directly over the roadway.
Foley Library Friends Give Major Boost To Library
By Guy Busby February 19, 2026
Foley, Ala. — (OBA) — The Foley Public Library project receives a significant boost as the Friends of the Foley Library donate $40,000 to help purchase equipment for the new building. The funds come from the group’s recent record-setting book sale. Library leaders say the gift will help them better serve families...
Legendary Marine
By OBA Staff February 19, 2026
Gulf Shores, Ala. — (OBA) — The Anchored in Hope Gala promises a special night for the Gulf Coast community. The Arc of Gulf Coast Alabama hosts this important event. It aims to bring people together in connection and celebration. Funds will support the expansion of programs for individuals with disabilities.
Christian Service Center
By OBA Staff February 19, 2026
Gulf Shores, Ala. — (OBA) — The Christian Service Center invites the community to enjoy a meal for a good cause at its annual spaghetti dinner later this month. The event promises an evening of food, fun, and fellowship while supporting local families in need. Dine-in and drive-through options will be available...
Orange Beach High School’s Lee Steele
By OBA Staff February 18, 2026
Orange Beach, Ala. — (OBA) — Orange Beach High School’s Lee Steele has been named the AHSAA Mobile Area Athlete of the Week, presented by Scout Program Management. The standout sophomore has quickly become one of Alabama’s most promising young athletes, earning recognition for his leadership and record-setting...
Archery Event Extends Foley Contract Through 2031
By OBA Staff February 18, 2026
Foley, Ala. — (OBA) — The Archery Shooter’s Association and Foley Sports Tourism are maintaining their successful partnership. The two organizations have signed a five-year extension to keep the nationally recognized Hoyt/Easton Pro/Am tournament in Foley through 2031. Leaders say the decision continues...
Gulf Shores Public Beach
By OBA Staff February 18, 2026
Gulf Shores, Ala. — (OBA) — In Monday night’s city council meeting, Gulf Shores moved closer to a more walkable West Beach, a larger and improved high school theater, and a series of smaller but meaningful quality-of-life upgrades that will impact everything from landfill operations to storm preparedness and traffic...
Planning Commission
By John Mullen February 18, 2026
Foley, Ala. – (OBA) – A busy and growing corner in Foley is about to grow some more. Developers hope to add a gas station to the new Publix shopping center at the intersection of the Foley Beach Express and County Road 20/Miflin Road. The new store would be south of Progress, at the center's southern exit.
Orange Beach Girls Basketball Team - Photo by Brent Williams, Wolf Bay Media
By John Mullen February 17, 2026
Orange Beach, Ala. – (OBA) – Mike Chase has two players who can legally drive a car. The rest are too young to hold a driver’s license. And while his Orange Beach Lady Makos record – 15-17 – indicates a young team, that young team is heading to Montgomery for the regional tournament as one of the sweet 16 left...
Orange Beach Boys Basketball Team - Photo by Brent Williams, Wolf Bay Media
By John Mullen February 17, 2026
Orange Beach, Ala. – (OBA) – In just two years as the Orange Beach boys basketball coach, veteran Chris Laatsch’s teams have set school records for wins each year. Laatsch’s team had 17 wins last year, including a trip to the Elite Eight, and, so far, 26 this year, with a Sweet 16 berth in the regionals coming up.
Show More